Brief Description:

Bridge replacement project delivered for Adman Group on the L3001, involving the demolition of a structurally failing bridge and the construction of a new reinforced structure using precast elements, in-situ works, and road reinstatement.

Project Sector:

Bridge Works

Year Completed:

2025

Client:

Adman Group

Designer:

Malachy Walsh & Partners

Location:

L3001, near Edenderry, Co. Offaly

Project Role:

Main Contractor

Tower Plant & Civil Engineering Ltd was appointed as Main Contractor to deliver the replacement of a structurally failing bridge on the L3001. The project was completed under a full road closure managed by Tower to ensure public safety and efficient delivery.

The works included:

  • Demolition of the existing bridge structure
  • Installation of precast MY4 bridge beams and MYE4 edge beams
  • Construction of an in-situ concrete deck
  • Installation of high parapets and crash barriers
  • Scaffolding installed on both sides of the bridge to provide access and ensure safe execution of key operations
  • Full road resurfacing, including approach roads
  • Use of a temporary steel crash deck to catch debris during demolition, eliminating the need for river diversion

The successful completion of this project restored a vital local route and improved long-term safety and durability for road users.